All guides

Delivery

A realistic 6–12 month London extension timeline

Most London extensions take 8–12 months from the first architect meeting to moving the furniture back. Here is every stage with real week numbers, the checklist for each, and the delays that are specific to London.

12 min read· Updated July 2026· London-specific

Timelines are the second thing every London homeowner underestimates, after cost. A single-storey rear extension is sold as "three to four months on site" and that part is often true — but the four months of design, twelve weeks of planning and eight weeks of party wall administration in front of it are equally real. Here is the honest calendar.

46–50 wks
Brief to handover
typical inner London rear extension
16–18 wks
On site
mid-spec 25–30 m²
8 wks
Party wall minimum
Section 2 notice period
4–8 wks
Steel lead time
order at contract signature
The whole programme on one chart
Mid-spec 28 m² rear extension, inner London, full planning route · Week 0 – week 50
Brief and feasibilitywk 03
Measured survey booked 3–4 weeks out in spring and autumn
Design developmentwk 38
Design frozen; engineer sizes steel for submission
Planning or LDCwk 820
Add 2–3 weeks of validation queue at busy boroughs
Technical designwk 1624
Overlaps planning — Building Control and construction details
Party wall notices and Awardwk 1424
Serve in parallel with planning, not after it
Tender and appointmentwk 2228
Tenders returned in 3–4 weeks, then interviews
On sitewk 2846
18 weeks from strip-out to practical completion
Snag, sign-off, handoverwk 4650
Retention held 6–12 months after this

Phase 1 — Brief and feasibility (weeks 1–3)

  1. 1

    Write the brief before you meet an architect

    Week 1

    One page: how you cook, eat and work at home; must-haves; the budget you will actually spend; the date you need to be finished by.

  2. 2

    Book the measured survey

    Week 1

    Half a day on site, two weeks for the CAD file. London survey firms are booked 3–4 weeks out in spring and autumn.

  3. 3

    Two or three feasibility options

    Weeks 2–3

    Not one preferred scheme. Options force the trade-offs into the open while changing them is still free.

  4. 4

    Sanity-check against per-m² benchmarks

    Week 3

    If the favoured option is 40% over budget at benchmark rates, fix it now — not after planning.

Phase 2 — Design development (weeks 3–8)

Before you submit anything
  • Design frozen and signed off by both ownersYou

    Every later change costs money and weeks. Sign the plan.

  • Planning drawings completeArchitect

    All elevations, sections, dimensioned depth and eaves height, materials schedule.

  • Structural engineer engagedEngineer

    Indicative steel and foundation strategy for the submission, so the scheme is buildable as drawn.

  • Pre-application advice, if marginalOptional

    £250–£800 and 4–6 weeks. Worth it for ambitious or precedent-free schemes.

  • Neighbours briefed informallyYou

    Before the council's consultation letter arrives, not after.

Phase 3 — Planning or LDC (weeks 8–20)

Determination times by route
RouteStatutoryLondon reality
Lawful Development Certificate8 weeks6–8 weeks
Householder planning8 weeks10–14 weeks in Camden, Islington, Hackney, K&C
Prior approval (larger single-storey)42 days6–7 weeks
Conservation area / objections8 weeks12–20 weeks

Phase 4 — Technical design (weeks 16–24, overlapping)

  • Building Control application — council or Approved Inspector.
  • Structural engineer issues construction calculations and details.
  • Party Wall notices served — allow two months minimum before start.
  • Drain build-over agreement applied for, where a shared drain is crossed.
  • Tender pack issued to three or four vetted builders, with a full schedule of works.

Phase 5 — Tender, appointment, mobilisation (weeks 22–28)

  1. 1

    Issue an identical pack to every builder

    Week 22

    Same drawings, same schedule of works, same provisional sums. Different packs make the returns incomparable.

  2. 2

    Tenders returned

    Weeks 25–26

    Three to four weeks is realistic. Anyone who prices a London extension in 48 hours has not read the drawings.

  3. 3

    Post-tender interviews

    Week 26

    Meet the site manager who will actually run your job, not only the salesperson. Ask to visit a live site.

  4. 4

    Contract signed

    Week 27

    JCT Homeowner or Minor Works, with a stage payment schedule tied to completed work and 2.5–5% retention.

  5. 5

    Mobilisation

    Week 28

    Hoardings, welfare, skip and parking permits, and the long-lead order for steel and glazing on day one.

Phase 6 — On site (weeks 28–46)

18-week site programme, 25–30 m² rear extension
Site weeks, not project weeks · Week 0 – week 18
Strip-out, protection, welfarewk 02
Dust screens, floor protection, temporary kitchen set up
Groundworks and drainagewk 25
Party wall surveyor's schedule of condition inspection before dig
Structural shell and steelwk 59
Brickwork, blockwork, beam installation, padstones
Roof, glazing, watertightwk 912
First fix electrics and plumbing follow the envelope closing
Plaster, screed, second fixwk 1215
Screed drying time governs the floor finish date
Kitchen, joinery, decorationwk 1518
Kitchen template dates are fixed weeks in advance

Phase 7 — Snag, sign-off and handover (weeks 46–50)

Do not release the final payment until you hold all of these
  • Snag list walked and signed offBoth

    Walk it in daylight, with the site manager, room by room.

  • Building Control completion certificateBuilder

    The document your buyer's solicitor will ask for. No certificate, no final payment.

  • Party wall post-works inspectionSurveyor

    Surveyor confirms no damage against the schedule of condition.

  • Electrical installation certificate and gas safety recordBuilder

    Part P certification and any Gas Safe work notified.

  • Glazing, roof and appliance warrantiesBuilder

    Registered in your name, with serial numbers.

  • As-built service drawingsYou

    Photographs of first fix before plaster are worth more than any drawing later.

  • Retention agreed in writingBoth

    2.5–5% held for 6–12 months for defects.

Serve your party wall notices while the council still has your planning application. Two months of statutory waiting can either run in parallel or bolt onto the end — that choice is yours, and it is free.

The single most useful piece of timeline advice

What legitimately compresses the programme

Do this
  • Serve party wall notices in parallel with planning
  • Take the PD + LDC route where the design allows — saves 4–6 weeks
  • Order steel, glazing and bespoke kitchens at contract signature
  • Use design-and-build under one contract to remove the tender gap
  • Move out during first fix — a builder not tiptoeing around a family runs 15–25% faster
Avoid this
  • Change the design after tender
  • Leave kitchen and bathroom selection until the shell is up
  • Under-brief neighbours and negotiate party wall dissent mid-build
  • Split the contract across many trades with no lead contractor
  • Book a holiday for the week of practical completion
+Can a London extension really be done in six months?

Yes, if the works are permitted development, you use design-and-build, party wall notices are served early and the design never changes. Twelve months is more common with full planning.

+How long is the build itself?

Sixteen to eighteen weeks on site for a mid-spec 25–30 m² rear extension. A side return alone can be twelve to fifteen; a double-storey rear runs twenty-two to thirty.

+Should we live in the house during the build?

Most families stay through groundworks and shell, then move out for first fix through plastering. That window is the dustiest and the noisiest, and moving out speeds the site up.

+What is the best time of year to start on site?

Late winter or early spring. Groundworks in deep winter risk frost delays, and you want the watertight envelope closed before the following autumn.

+Who owns the programme?

The contractor produces it; you approve it and hold them to it at weekly site meetings. Ask for a one-page updated programme at every meeting — the drift shows up there first.

Ready to price your project properly?

Send us your postcode and a few details — we'll come back with a fixed range and a shortlist of KYB-verified builders.

Keep reading

Call now WhatsApp