How much does a house extension cost in London (2026)?

A realistic 2026 view of what a rear, side-return, wraparound or double-storey extension costs in Greater London — plus a step-by-step method to build your own budget line by line.

14 min read· Updated July 2026· London-specific

The honest answer before any caveats: a mid-spec single-storey rear extension in inner London lands between £3,400 and £4,600 per square metre once professional fees, statutory costs and contingency are included — excluding VAT. For a 25 m² kitchen extension in Hackney or Wandsworth that means roughly £90,000 – £130,000 plus VAT.

£3.4k–£4.6k
Per m² inner London
mid-spec, incl. fees, ex VAT
+15–20%
Prime central uplift
K&C, Westminster, prime Camden
10–15%
Contingency to hold
non-negotiable on Victorian stock
20%
VAT on top
extensions are standard-rated

Step 1 — Fix your footprint and finish level first

Every credible budget starts with two numbers: how many square metres of new floor area, and which finish tier you are buying. Everything else is derived. Write both down before you talk to anyone.

Finish tiers — what each actually buys in London
TierGlazingKitchenFloor / heatingPer m² ex VAT
ValueOff-the-shelf aluminium bifolds, standard rooflights£10k–£15k trade kitchenEngineered oak, rads or basic UFH£2,900–£3,500
MidSlim aluminium sliders, 2 large rooflights£18k–£28k with integrated appliancesLarge-format tile, zoned UFH£3,400–£4,600
HighBespoke steel-look or structural glass£45k+ bespoke joineryStone or micro-cement, multi-zone UFH£5,000–£7,500

Step 2 — Pick the right per-m² base rate for your type

London costs vary more by finish and complexity than by extension type — but some types carry structural or planning overhead that shifts the rate.

Delivered cost per m² by extension type (inner London, ex VAT)
Includes shell, fit-out, professional fees and statutory costs. Excludes VAT and furniture.
Side return (10–20 m²)£3.3k£5k
Small footprint, high proportion of expensive elements — steel, roof glazing, two party walls.
Rear extension (20–35 m²)£3k£4.8k
Best £/m² efficiency: shell cost spread over a larger floor area.
Wraparound (30–45 m²)£3.3k£5.2k
Side return plus rear, with a more complex roof geometry and more glazing runs.
Double-storey rear (40–70 m²)£3.5k£5.5k
Deeper foundations and heavier steel, but roof cost shared across two floors.

Step 3 — Apply your borough tier multiplier

London labour and logistics are not uniformly priced. We quote against three tiers:

Borough tiers and what drives the difference
TierExamplesAdjustmentWhy
Prime centralK&C, Westminster, prime Camden+15% to +20%Permit-only parking, restricted access, conservation detailing, premium subcontractors
Inner LondonHackney, Islington, Lambeth, Southwark, Wandsworth, Tower Hamlets, H&F, Haringey+5% to +8%Party Wall Act near-universal, rear-only material access, tight site setup
Outer LondonBarnet, Bromley, Croydon, Ealing, Hillingdon, RichmondBaseline (0% to −5%)Side gate access, on-plot parking, easier deliveries and spoil removal

Step 4 — Add the costs that sit on top of the build

An estimator quoting only shell plus fit-out is quoting incompletely. Add every one of these:

  1. 1

    Professional fees

    10–14% of build

    Architect (RIBA stages 1–4), structural engineer, planning consultant where needed, and project management. Design-and-build firms bundle these; independent architects invoice separately by stage.

  2. 2

    Planning fees

    £129–£258

    £258 for a householder application in England (2026); £129 for a Lawful Development Certificate. Pre-application advice, where offered, runs £250–£800 extra.

  3. 3

    Building Control

    £850–£2,200

    Council or Approved Inspector. Includes plan check and site inspections through to the completion certificate — insist you receive that certificate.

  4. 4

    Party wall

    £900–£3,500 per neighbour

    One agreed surveyor is cheapest. If your neighbour appoints their own, you pay both. Terraces with two adjoining owners can reach £3,000–£7,000.

  5. 5

    Structural engineer

    £750–£1,800

    Beam and foundation calculations plus construction details. Cheaper if instructed early alongside the planning drawings rather than after tender.

  6. 6

    Contingency

    10–15%

    Hold it as real cash, in your account, not in the builder's price. On pre-1930 London stock, ground conditions and hidden rot are normal, not exceptional.

  7. 7

    VAT at 20%

    Standard-rated

    Extensions to existing dwellings are standard-rated. Some works on listed properties or long-empty homes vary — assume 20% until an accountant proves otherwise in writing.

  8. 8

    CIL

    Usually £0

    Community Infrastructure Levy is normally nil under 100 m² of new floor area, but check your borough's charging schedule and file the exemption form on time.

Step 5 — Test the shape of your budget

Once you have a total, sanity-check its distribution. A London extension budget that puts more than a quarter of the money into glazing, or under 10% into fees and contingency, is a budget that will move.

£160k
Healthy shape of a £160,000 London extension budget (ex VAT)
  • Shell — groundworks, structure, roof, envelope42%
  • Glazing, rooflights and external doors13%
  • Kitchen, joinery and appliances17%
  • M&E — electrics, plumbing, UFH, ventilation12%
  • Fees, statutory costs and contingency16%

Worked example: 28 m² rear extension, mid-spec, Hackney

Open-plan kitchen-diner, bifolds, two rooflights, underfloor heating, party walls both sides.

Line-by-line build-up
LineBasisAmount
Shell28 m² × £3,600/m²£101,000
Fit-out modifierOpen-plan + feature glazing£28,000
Professional fees~11% of build£15,000
StatutoryPlanning, BC, party wall ×2, structural£6,000
Contingency12%£18,000
Total ex VAT£168,000
VAT20%£33,600
Total inc VAT£201,600

Same brief in Ealing: typically 6–10% lower. In Kensington & Chelsea: 15–20% higher, mostly labour, parking suspensions and heritage detailing.

Step 6 — Compare quotes on a like-for-like basis

Quote comparison checklist
Run every tender through this before you compare bottom lines.
  • Is VAT shown separately?You

    A net quote next to a gross quote is a 20% illusion. Normalise both to ex-VAT.

  • Are provisional sums identified?Builder

    PROV and PC sums for kitchen, glazing and landscaping should be listed with the allowance stated.

  • Who pays statutory fees?Builder

    Planning, Building Control, party wall and skip/parking permits — named, not assumed.

  • Is muck-away and spoil removal included?Builder

    London spoil disposal is £180–£320 per tonne removed including permits.

  • Is scaffolding priced for the full duration?Builder

    Ask for the weekly hire rate beyond the allowed period.

  • Is making-good to the existing house included?Builder

    Plastering, decorating and floor levelling where new meets old — the classic variation.

  • Is there a stage payment schedule with triggers?Both

    Payments against completed work, never against calendar dates.

  • Is retention held?You

    2.5–5% for 6–12 months after practical completion.

The cheapest quote on the table is almost always the least complete one. Price the same scope three times before you price three different scopes once.

What we tell every homeowner on the first call

The three costs homeowners forget

Forgotten costTypical London rangeWhen it lands
Kitchen and appliances£12,000–£25,000 mid-specWeek 14–16, after the money feels spent
Landscaping and garden reinstatement£3,000–£8,000Final two weeks on site
Temporary accommodation8–14 weeks of London rentFirst fix, when dust and no kitchen collide

How to bring the London number down without cheapening it

Do this
  • Design for efficiency — a well-planned 22 m² beats a badly planned 32 m² and saves £30k+
  • Repeat details: the same rooflight and door spec twice is cheaper than two bespoke ones
  • Use standard glazing module sizes; bespoke prices 30–50% higher for the same finish
  • Buy design-and-build under one contract to remove the coordination gap that generates variations
  • Order long-lead steel and glazing at contract signature
Avoid this
  • Value-engineer the shell to fund a showpiece rooflight
  • Change the design after tender — every post-tender change is priced without competition
  • Leave the kitchen out of the budget so the headline looks lower
  • Let contingency live inside the builder's price
  • Accept a lump-sum quote with no schedule of works behind it

How our estimator handles all of this

The calculator layers borough tier, extension type, finish, features and party wall logic on top of shell and fit-out benchmarks, then adds fees, statutory costs and contingency automatically. The quote page shows the full itemised breakdown — nothing bundled — with VAT separated so you can compare like-for-like against builder quotes.

+Is £2,500 per m² ever realistic in London?

Only for a value-spec extension in outer London with side access, standard glazing, no party wall complications and a trade kitchen supplied by the homeowner. Treat it as the floor, not the benchmark.

+Should I hold contingency or let the builder price risk?

Hold it yourself. A builder pricing risk inside a fixed sum will price it at the pessimistic end and keep the difference; you will never see it back.

+Do I pay VAT on architect and engineer fees too?

Yes — professional fees are standard-rated. Budget VAT across the whole project, not just the build contract.

+How much does an extension add to a London house value?

Typically 6–11% on a mid-market terrace for a well-executed kitchen extension, and less in prime central where the £/m² of existing space is already very high. Never treat uplift as a guaranteed return.

+When is the cost fixed?

Realistically at contract signature on a full technical package — structural details, glazing schedule, kitchen and electrical layouts. Fixing a price off planning drawings alone invites variations.

Ready to price your project properly?

Send us your postcode and a few details — we'll come back with a fixed range and a shortlist of KYB-verified builders.