All guides

Kits

What's in a loft conversion kit

A structural loft kit is the difference between a self-build that stays on programme and one that stalls at first fix waiting for a steel fabricator. This is the full playbook — what a proper kit includes, what it costs in 2026, and how it gets you to building-regs sign-off faster.

12 min read· Updated July 2026· London-specific
Structural loft conversion kit components — steel frame, insulated roof cassettes and dormer sections ready for craning in
A pre-engineered rear dormer kit — steel frame, insulated cassettes and dormer cheeks arrive cut, drilled and numbered.

A loft conversion kit is rarely just "some timber and a few sheets of insulation." It's a pre-engineered, building-regs-ready structural package — steelwork, floor joists, insulated roof cassettes and dormer framing, all designed off your specific roof survey and delivered ready to crane or hand-carry in. Get the kit right and a self-build team can close the weathertight envelope in days, not weeks.

£38k–£95k
Typical kit price
structural package only, ex VAT
£1.6k–£2.9k
Per m² inner London
kit + self-managed labour + fees
3–5 wks
Kit lead time
from signed structural drawings
+20–25%
Typical value uplift
extra double bedroom + ensuite

What you're actually buying

Homeowners tend to price a loft conversion against a builder's all-in quote. A self-build kit unbundles that number: you buy the engineered structure and building-regs pack directly, then manage or sub-contract labour yourself. Here's how a typical £62,000 rear dormer kit and build breaks down.

£62k
Where a £62,000 self-build rear dormer project goes
  • Structural kit — steel, joists, cassettes, dormer frame44%
  • Windows, rooflights & external cladding15%
  • Labour — crane day, erection, weathertight close-in18%
  • M&E — electrics, plumbing, stair, insulation top-up12%
  • Building control, structural engineer sign-off & contingency11%

2026 cost ranges by loft type

Kit + self-build delivered cost by loft type (ex VAT)
Greater London averages. Prime central boroughs run 10–20% above these bands for cladding and finishes; outer London sits 5–10% below.
Rooflight / Velux conversion (no dormer)£28k – £46k
No structural roof alteration — the fastest and cheapest kit to close in.
Rear dormer (single or L-shaped section)£38k – £68k
The London default. Steel ridge beam, insulated cassettes, one dormer frame.
L-shaped dormer (main + rear addition)£52k – £88k
Two linked dormer frames over the original roof and the rear outrigger.
Hip-to-gable£46k – £78k
Rebuilds the hipped end as a vertical gable before the dormer or rooflights go on.
Mansard£62k – £95k
Full rear-slope rebuild at 72°; usually needs full planning and heavier steel.

The four loft types and what changes in the kit

Most London terraces and semis share a handful of roof geometries. Which one you have decides the structural kit — steel spans, dormer cheeks, ridge beam sizing and how much of the original roof stays in place.

Loft type selection by roof and headroom
Roof conditionKit that fitsWhyWatch
Good existing head height (>2.3 m at ridge)Rooflight / Velux conversionNo structural roof alteration needed, kit is glazing, joists and stair onlyConfirm 1.9 m minimum head height over the stair run first
Standard 45° pitched roof, rear elevation onlyRear dormer kitSteel ridge beam plus one dormer frame gives full head height across the rear thirdParty wall Section 2 applies where the dormer cheek sits on the shared wall
Rear addition + main roof both usableL-shaped dormer kitTwo dormer frames linked at the valley maximise usable floor areaValley detailing is the single most common leak point — spec it carefully
Hipped roof end (no gable wall)Hip-to-gable kit first, then dormerRebuilding the hip as a gable adds width before any dormer goes onCheck the neighbour's flank wall condition before cutting into the hip

Order the kit off a laser survey, not off the estate agent's floorplan. A 40 mm error at ridge level moves every steel length in the package.

— A rule we apply on every self-build loft kit spec

Structure: what the kit contains, piece by piece

A proper structural loft kit is a numbered package designed off your specific roof survey — not a generic timber pack. Every component ties back to the structural engineer's calculations and the building-regs submission.

Kit components — supplied, cut and numbered
Indicative London supply pricing, 2026, structural kit only.
Ridge beam and steel bearings£3.8k – £7.2k
Carries the new floor loads down to the existing walls without overloading old rafters.
Insulated floor joists (I-beam or LVL)£6.5k – £12.5k
Deep enough to carry acoustic insulation and services without dropping a ceiling below.
Dormer frame — timber or SIP cassette£8.5k – £18k
Pre-insulated cassette panels close in faster and hit Part L u-values without site cutting.
Roof cassettes over the retained roof slope£4.2k – £9.5k
Factory-insulated panels replace stripped-out rafters section by section.
Staircase structural opening and trimmers£1.8k – £4.2k
Usually the most disruptive single element for the floor below — plan the route early.

Programme: from survey to weathertight

  1. 1

    Laser survey and structural design

    Weeks 1–2

    A measured survey feeds the structural engineer's calculations, which in turn size every steel and cassette in the kit. Skipping the laser survey in favour of estimated dimensions is the most common cause of an on-site kit mismatch.

  2. 2

    Kit manufacture

    Weeks 3–7

    Steel fabrication and cassette manufacture run in parallel once drawings are signed off. London lead times are 3–5 weeks — order at design sign-off, not at strip-out.

  3. 3

    Strip-out and temporary roof

    Week 8

    Existing tiles, felt and rafters over the work area come off under a temporary weatherproof cover before the steel goes in. A dry week matters more here than almost anywhere else in the build.

  4. 4

    Crane-in and erection

    Weeks 8–9

    Steel and pre-insulated cassettes are craned or hand-winched into place and fixed to the engineer's sequence. A typical rear dormer kit closes the structural shell in three to five working days once craned.

  5. 5

    Weathertight close-in

    Weeks 9–11

    Membrane, battens, tiles or cladding, and the dormer's flat roof covering go on. Reaching weathertight here means internal trades can start regardless of weather for the rest of the build.

Where self-build loft projects go wrong

Do this
  • Order the kit off a laser survey with the structural engineer's sign-off, not off a rough sketch.
  • Confirm your building control route (full plans or building notice) before the kit is manufactured.
  • Serve party wall notices two months before crane day if any dormer cheek sits on a shared wall.
  • Book the crane and scaffold together — a mismatch in dates is the single most common self-build delay.
  • Agree a written scope with your erection labour before the kit lands on site.
Avoid this
  • Assuming permitted development covers you. Article 4 areas, flats and roofs facing a highway all change the rules.
  • Changing the dormer footprint after the kit has gone into fabrication.
  • Ignoring the stair trimmer position until the kit is on site — it decides which room below loses ceiling height.
  • Ordering rooflights separately from the kit without checking upstand compatibility.
  • Leaving fire escape and means-of-warning provisions out of the building control submission.

A worked self-build example

24 m² rear dormer loft, Victorian terrace, Zone 2 — kit plus managed labour
ElementScopeCost (ex VAT)
Survey & structural designLaser survey, structural calculations, building control pack£3,200
Structural kitRidge beam, floor joists, dormer cassette frame, roof cassettes£27,400
Windows & rooflightsDormer casement windows, two flat rooflights on the retained slope£6,800
Cladding & roof coveringSlate or tile to match, dormer cheek cladding, EPDM flat roof£5,900
Erection labourCrane day, three-week fix, weathertight close-in£9,600
M&ENew circuit, ensuite plumbing, ventilation, insulation top-up£6,300
StaircaseNew structural opening, joinery staircase£4,100
Building control & party wallFull plans application, inspections, party wall award£2,600
Contingency8% on kit and labour£3,900
TotalDelivered, excluding VAT£69,800

Frequently asked

+Can I project-manage a loft kit build myself?

Yes — that's the point of a structural kit. You still need a structural engineer's sign-off, a competent erection team for crane day, and building control inspections at set stages, but you are not paying for a main contractor's overhead and margin on top.

+Do I need planning permission for a loft conversion kit?

Most rear dormers up to 40 m³ (terrace/semi) or 50 m³ (detached) are permitted development. Mansards, hip-to-gable on corner plots, and anything in a conservation area or Article 4 direction usually need full planning. Always confirm with your borough before ordering the kit.

+How long does the structural kit take to arrive?

Three to five weeks from signed structural drawings for a standard rear dormer. Mansard and L-shaped kits with more steel can run six to eight weeks — order at design sign-off.

+What is the single most expensive mistake?

Ordering the kit before the structural engineer has finalised bearing positions. A late change to a steel length or dormer cheek means re-fabrication and a lost slot in the manufacturer's schedule.

+How do I know a kit is genuinely building-regs-ready?

Ask for the structural calculations, fire strategy and u-value compliance documents before you order — not after. Every kit on our platform ships with a full building control submission pack.

Ready to price your project properly?

Send us your postcode and a few details — we'll come back with a fixed range and a shortlist of KYB-verified builders.

Keep reading

Call now WhatsApp